JIGAWA STATE MINISTRY OF WORKS AND TRANSPORT- INVITATION TO PREQUALIFICATION FOR ROAD CONSTRUCTION AND REHABILITATION

JIGAWA STATE GOVERNMENT
MINISTRY OF WORKS AND TRANSPORT
BLOCK B, Q4 NEW SECRETARIAT, PMB 7023 DUTSE
REF: MOW&T/POL/S/GEN/150/1
INVITATION TO PREQUALIFICATION FOR ROAD CONSTRUCTION AND REHABILITATION

In line with His Excellency Governor Umar Namadi’s 12-point Agenda among which is Urban Infrastructure and Rural Transformation. The Jigawa State Ministry of Works and Transport is hereby inviting interested reputable civil engineering construction companies to submit prequalification documents for the following proposed roads construction and rehabilitation projects across the state.

A. CONSTRUCTION OF RURAL FEEDER ROADS
1. Chuwasu chakwakwalwa-Zangon Maje Feeder Road 25.8km
2. Kankare-maiturmniyya-Kanjau-Gnajara-Garin barka waith spur from Maituruminya to Duhuwa feeder road 21.1km
3. Sada-Dankari-unguwar Mallam-Kuda Feeder road 13.5km
4. Kiri-Nahuce-bardo-sabongarin Takanebu feeder road 15.3km
5. Babban Sara-Malam Bako-Shabaru-Albasu Feeder road 28.2km
6. Kwanar Gawo-Mawa-Kataudi-Ayan-Minari-Dawaya-Zugo-kaigameri-Keban-Une-Unik Gana-Mainawa-Hinge feeder road 28km
7. Gatare-Kazura-Abani feeder road 12.3km
8. Kiri Kassamma-Gayin-Kukadabo-Matafari – Daglifani feeder road 15.5km
9. Andaza-Duhuwa-Katanga-Baranda feeder road, 17.5km
10. Tsakuwawa Koya K/hausa feeder road, 30km
11. Maiduguri Road Along Alu Farm -Lemo-Janruwa-Kangire Road 10.5km
12. Abaya-Dagwaje-Atawame Feeder Road 13km
13. Gwaram-Sangara-Gadala-Malaji 6km
14. Kila-Jigawa-Sakuwa Feeder Road 8.1km
15. Kwanar Madoblya – Bagadaza-Zamandiri Road 9.5km

B. DUTSE CAPITAL ROADS 15KM

C. TOWNSHIP ROADS IN URBAN CENTERS
1. Construction of Aujara Township Road 4km
2. Construction of Fagam Township Road 3km
3. Construction of Bulangu Township Road 3km
4. Construction of Gandun Sarki Township Road 3km
5. Construction of Dansure Township Road 3km
6. Construction of Sankara Township Road 3km
7. Construction of Roads Network in As-Salam University 3km

D. UPGRADING OF RURAL FEEDER ROADS
1. Construction of Kwanar Duzau -Gwaron Maje Road 19.5km
2. Construction of Firji-Guntal-Buntusu-Dan’abzin Road 29.1km
3. Construction of SUBEB-Korau-Madobi Shuwarin Road 18km
4. Construction of Kwanar Idanduna – Kadowawa – Gangawa- Nahuce Kwarnar Olayinka Road 34.7km
5. Construction of Tarabu – Matarar Alhazai – Malanta – Sabon Garin Sawo-Sawo-lyo-Gishinawo – Gafta Road 22.5km
6. Construction of Tage -Limawa Makera Mizan – S/Gida Kwatalo Road 13.3km

E. NEW CONSTRUCTION OF REGIONAL ROADS
1. Construction Of Arbus Girbobo – Gwalerima- Garin Bukar- Marma Girte Gine-Kunderan Road 33.5km
2. Malam Madori – Gari Uku – Kanya Babba – Malorin Kasim – Garin Maigawo-Kubuna – Sumburtu-Diginsa Road 34.5km
3. Dundubus-Yanjaji – Wangara Road 15km
4. Jahun Takalafiya – Zareku Kafin Hausa With Spur From Takalafiya To Dangyatum Road 38km Construction Of Kukayasku Malam Abba – Katuka – Garin Kwalandi Road 34.5km
5. Farun Daba – Maitsani – Baauzini-Kafin Chiroma-Gallu Babba – Gallu Karama-Karkarna Road 13.2km

F. ASPHALTIC CONCRETE OVERLAY
1. Hadejia-Garun Gatas -Dolen Kwana road 29.2km
2. Birnin Kudu-Sundumina-Kiyawa Road 47.4km
3. Gumel-Babura Road 45km
4. Gada-Farin Daba – Dandi – Achilafiya Road 28.5km
5. Rehabilitation of the sections Achilafiya – Dandi – Kanya Babba Road 74.2km

SCOPE OF WORK
The Scope of works includes but not limited to the following: Clearance, Filling, Construction of Drainages, Culverts, Bridges, provision of 150mm lateritic sub-base and base course on carriageway and shoulder, surface dressing/asphaltic concrete overlay, and associated Road furniture.

MANDATORY REQUIREMENTS
1. Certificate of Incorporation with Cooperate Affairs Commission
2. Certificate true copy memorandum and article of association
3. Evidence of registration with Jigawa State Due Process and Project Monitoring Bureau.
4. Registration with Jigawa State Ministry of Commerce (Business premises)
5. Tax clearance for the last three years;
6. Audited accounts for the last one (1) year;
7. VAT Registration and Evidence of Past Remittance.
8. Evidence of financial capability and banking support.
9. Company average annual turnover of not less than N250Million for category A, N500m for category C and N2 Billion for category B,D, E and F.
10. Evidence of similar project executed (letter of award and completion certificate) at least three (3) in the last five (5) years;
11. Company’s profile including names of key professional staff registered with relevant professional bodies;
12. That the companies have fulfilled all obligations to pay taxes, pensions and social security contributions;
13. A sworn affidavit certifying as follows:
a. That the document submitted for pre-qualification exercise is not only genuine and correct.
b. That none of the directors/partner of the company has been convicted by any court of law.
c. That the company is not bankrupt.
d. That none of the officers of Jigawa State/Local government is a present or former director of the company.
e. Any other relevant information that will help in determining the company’s suitability for the work;
The Ministry reserves the right to accept or reject any application at any time without incurring any liability.

This advert shall not be construed as commitment on the part of the Jigawa State Ministry of Works nor shall it entail a company to make any claim(s) whatsoever and/or to seek any indemnity by virtue of such company having responded to this advertisement.

Method of Submission:
The Prequalification documents have to be submitted on or before 12noon Monday, 10th June 2024 to the Director Procurement, Ministry of Works and Transport, Block B, New Secretariat Complex, Dutse.

Opening Time:
The Prequalification documents are to be open immediately after the closing of the submission by 12Noon at Ministry Conference Hall.

Signed:
Secretary Ministerial Tender Board
Ministry of Works and Transport, Dutse